Monday, March 2, 2015

Project to connect 150,000 to grid


2 March 2015


Germany’s development bank Kfw, contributing $22.2 million, and the Cambodian government via Electricity du Cambodge paying for the rest. The project was completed in two stages. The first involved the construction of a power substation in Kampot and the Takeo power station. The second stage saw the setting up of a 587-kilometre distribution network to communes in Takeo, Kampot and Kampong Speu provinces.

Source:
http://www.phnompenhpost.com/project-connect-150000-grid